Our News

Industry Insights & Corporate News

Ascent Petrochem Holdings Co., Limited

Green Catalytic Method for Pollution Reduction Retrofitting Bromochloromethane Production Lines

In 2018, a 22-kta bromochloromethane (BCM) production line at a European halogenated solvents facility underwent partial decommissioning of its photochlorination reactor battery to enable installation of a heterogeneously catalyzed halogen exchange stage. The legacy route contacted a chilled (10°C) liquid bromomethane stream with gaseous chlorine in a two-stage borosilicate glass bubble column illuminated by UV lamps emitting at 254 nm; this generated a crude product containing 12–15 wt% over-chlorinated species—predominantly chloroform and carbon tetrachloride—alongside 3–5 wt% dibromochloromethane, requiring a three-column azeotropic distillation train and a caustic/hypochlorite scrubber loop that produced 1.4 t of NaClO‑contaminated brine per tonne of BCM. The green retrofit replaces the photochemical step with a single-pass, downflow multi-tubular fixed-bed reactor loaded with a 0.5 wt% Pd/CeO2 catalyst shaped as 3.2 mm trilobe extrudates (BET surface area 45 m²/g, crush strength 1.2 kg/mm per ASTM D4179‑21). Operating at 260–285°C and 2.1 bara with a weight hourly space velocity (WHSV) of 0.8–1.2 h⁻¹ and an HBr:CH2Cl2 molar feed ratio of 1.08:1, the catalytic system achieves 87% per-pass conversion of methylene chloride and a BCM selectivity exceeding 96% on a bromine basis, suppressing polyhalogenated byproduct formation to below 0.4 wt% in the reactor effluent. Heat of reaction (−85 kJ/mol) is removed by pumping a synthetic heat-transfer fluid (dibenzyltoluene) through the shell side at a velocity of 2.3 m/s, maintaining a radial ΔT across the 48 tubes (ID 25.4 mm, length 6.1 m) of ≤12°C. Catalyst load per tube is 8.5 L, giving a total bed volume of 408 L; the bed pressure drop at full throughput is 0.28 bar with a void fraction of 0.41 measured by mercury porosimetry. The retrofitted line eliminates aqueous waste generation at the reaction step entirely, recycles the HBr co-product via a 98.5% recovery compressor‑surge‑drum loop, and reduces specific energy consumption from 7.2 MJ/kg BCM to 4.1 MJ/kg, as verified by an ISO 50001:2018 energy baseline audit.

What Limits Adiabatic Temperature Rise in a Fixed-Bed Halogen Exchange Reactor?

The principal process safety constraint governing catalyst longevity and selectivity in the retrofitted BCM line is the control of the adiabatic temperature excursion that would follow a loss-of-cooling scenario. The dibenzyltoluene coolant circulation system relies on two 100%-capacity centrifugal pumps (design flow 45 m³/h at 3.2 barg) delivering the fluid to a shell-side distributor with 56 cross‑baffle passes; loss of both pumps — a single contingency event with a frequency quantified in the HAZOP as 8 × 10⁻³ per year — allows the exothermic halogen-exchange reaction to propagate with a computed adiabatic temperature rise of 143°C, elevating the bed centerline temperature from the steady-state hotspot of 310°C to 453°C within 47 seconds of flow interruption. At 453°C, the CeO2 support undergoes a phase transformation from tetragonal to cubic fluorite structure accompanied by a 38% loss in BET area and a simultaneous agglomeration of Pd crystallites from 2.8 nm to >15 nm, as measured by CO‑pulse chemisorption (ASTM D3908‑20), permanently reducing the catalyst’s activity coefficient to <0.3 of its virgin value. To arrest this runaway before the sintering threshold — defined as 400°C on the tube‑center thermocouple — the reactor is fitted with a dedicated quench system that injects 4.2 kg/s of sub‑cooled liquid CH2Cl2 directly into the feed manifold within 3.2 seconds of a confirmed pump failure signal, lowering the combined feed temperature to −22°C and quenching the bed to below 200°C in less than 25 seconds. The quench valve arrangement has a SIL‑2 rating per IEC 61511‑1:2016, using a 2oo3 voting logic on the coolant flow transmitters. Even during normal operation, the shell‑side coolant inlet temperature is trimmed to 220°C by a cascade controller whose cold‑fluid make‑up stream passes through a plate‑and‑frame heat exchanger (surface area 34 m²) cooled by a secondary glycol loop; a departure beyond ±5°C from the setpoint triggers a pre‑alarm that has been observed to activate on average 1.7 times per 1 000 operating hours during start‑up transients, typically resolved by operator adjustment of the make‑up valve travel from 12% to 18%. The effectiveness of this thermal management envelope has been verified by a full‑scale emergency shutdown test conducted during the 2021 commissioning campaign, wherein the bed centerline temperature peaked at 387°C and returned to 225°C within 52 seconds, well inside the catalyst safety window. The off-gas treatment train integrates a falling-film polypropylene‑lined absorber with 20 wt% sodium hydroxide solution to neutralize HCl and HBr vapors originating from the mild endothermic dehydrohalogenation side reactions that produce 0.7 vol% mixed hydrogen halides in the reactor vent. The absorber is designed for a maximum gas throughput of 420 Nm³/h at 60°C and a pressure drop of 15 mbar, using a structured packing with a specific surface of 250 m²/m³ (Mellapak 250Y) to achieve a Murphree vapor‑phase efficiency of 0.94 for HCl removal. Scrubbed gas exiting the column is routed through a 10 μm coalescing filter, a twin‑bed activated carbon treater (coconut shell carbon, iodine number 950 mg/g, bed depth 1.8 m each) and a thermal oxidizer operating at 860°C with a 0.8‑second residence time before discharge through a 30 m stack. Continuous emission monitoring per EN 15267‑3:2008 shows HCl stack concentrations of 0.8–1.5 mg/Nm³, HBr below 0.3 mg/Nm³, and total chlorinated VOCs (as methane equivalents, EPA Method 18) at 1.2 mg/Nm³, all of which are lower than the BAT‑AEL upper limits of 5 mg/Nm³ for HCl and 20 mg/Nm³ for TVOC specified in the EU BREF LVOC 2017 conclusions. The spent caustic scrubbing liquor, containing 12–14 wt% sodium chloride and 4–6 wt% sodium bromide, is concentrated in a single‑effect evaporator to 35 wt% total dissolved solids and sold as a mixed‑salt de‑icing brine, eliminating the former requirement for deep‑well disposal of 1.4 t saline waste per tonne of BCM.

When Hydrogen Bromide Recycle Rate Exceeds 98%, Material Compatibility Issues Arise

Achieving a steady‑state hydrogen bromide recycle ratio of 98.5% — necessary to avoid stoichiometric HBr make‑up and the associated bromine‑storage inventory — introduces a severe corrosive environment in the recycle compressor suction piping, where the gas stream at 0.6 barg and 32°C carries 120 ppmv of water vapor due to equilibrium saturation after the caustic scrubber. Under these conditions, the dew point of HBr‑saturated air is −4°C, and condensation of a 5–8 wt% hydrobromic acid film occurs on the inner wall of the DN 150 schedule 40S pipe whenever the ambient temperature drops below 8°C, which happens on 47 nights per year at the plant’s north‑German location. Hastelloy C‑276 (UNS N10276), selected for the main process piping, exhibits a corrosion rate of <0.03 mm/year in 80°C 10% HBr solutions under static conditions per ASTM G31‑72(2021) immersion tests, but the simultaneous presence of trace chlorides — 15 ppmv in the gas phase — accelerates pitting corrosion in the heat‑affected zones of orbital butt welds to a measured pit depth of 0.11 mm after 2 000 exposure hours, as revealed by phased‑array ultrasonic inspection (ASME Section V, Article 4) repeated every 6 months. To manage this risk, the suction piping downstream of the first isolation valve is constructed from zirconium Grade 702 (UNS R60702), which maintains a corrosion rate <0.005 mm/year even in 20% HBr at 85°C and carries a 1.2 mm corrosion allowance, reducing the predicted remaining life of the pipe to 28 years based on a linear pit‑growth model validated with 3‑sigma statistical confidence. The recycle compressor itself (a single‑stage centrifugal machine, 35 kW motor, impeller speed 11 800 rpm) employs a dry‑gas seal system purged with 3 Nm³/h of nitrogen and all wetted static components are manufactured from Inconel 625, whereas the inter‑stage cooler uses a welded plate‑and‑shell design with 0.5 mm‑thick 254 SMO (UNS S31254) plates. During the 2022 annual turnaround, a boroscope inspection of the compressor volute identified shallow, scattered pitting (0.04 mm average depth) attributed to a 4‑week shutdown period where the N2 purge was briefly interrupted, allowing acid condensation; this discovery prompted the addition of an automated, battery‑backed purge control system with 72‑hour autonomy meeting SIL‑1 requirements. Retrofit execution demands phased shutdown and hot‑tap tie‑ins on live chlorocarbon lines, coordinated with a 28‑day planned turnaround window. The first 72 hours are dedicated to process decontamination: the existing methylene chloride feed line (DN 100, 4.2 barg operating pressure) is blinded and flushed with 1,2‑trans‑dichloroethylene at 40°C for 24 hours to dissolve residual polymerized chlorocarbon deposits, a procedure validated by wiping with 4 cotton swabs and checking for non‑volatile residue ≤5 mg/m². Simultaneously, the BCM distillation column reboiler is re‑tubed with 22 mm OD 1.2 mm wall Duplex 2205 tubes to handle the new, drier feed quality. Hot‑tap operations on the HBr recycle header are performed at 1.8 barg using a pressurized welding enclosure purged with 99.999% nitrogen, with a continuous hydrocarbon LEL monitoring set to alarm at 10% LFL, and the 300 mm‑long branch is completed in 6.5 hours of continuous welding monitored by an independent API 579 integrity assessor. Once the catalyst tubes are installed and the reactor closure welds pass a helium leak test (leak rate <1 × 10⁻⁶ mbar·L/s under 3.5 bara), the catalyst is loaded under a dry nitrogen atmosphere using a dedicated 5 m³ hopper with a dust‑extraction shroud that maintains a residual oxygen level of <0.2 vol% at the fill nozzle, verified by a zirconia sensor. The loaded beds are reduced in situ by flowing 40 Nm³/h of a 5 vol% H2/N2 mixture at 300°C for 72 hours, with effluent water concentration monitored by a chilled‑mirror hygrometer until it stabilizes below 5 ppmv. Following reduction, a 48‑hour performance test with 100% methylene chloride feed at 70% design WHSV confirms a minimum BCM selectivity of 95.5% before the hot‑tap blinds are removed and production ramps to full capacity over 72 hours.

Evaluating Catalyst Pellet Integrity During Pressure Swing from 1.2 to 2.1 bara

The catalyst pellets in the 48 reactor tubes are subjected to a repetitive mechanical stress cycle each time the unit is depressurized for a scheduled shut‑down or a partial‑load turn‑down, because the tube‑side pressure oscillates between the normal operating value of 2.1 bara and the regeneration‑standby pressure of 1.2 bara. This 0.9 bar differential induces a radial stress of approximately 0.35 MPa on the 3.2 mm trilobe extrudates, calculated from finite‑element modeling of a packed bed with a tube‑to‑pellet diameter ratio of 7.9. Single‑pellet crush strength measured per ASTM D4179‑21 on 200 randomly sampled extrudates shows a mean of 1.17 kg/mm with a standard deviation of 0.14 kg/mm; the specification for acceptable attrition resistance requires a lower 3‑sigma limit of 0.85 kg/mm to avoid generation of fines that would migrate into the downstream distillation column reboiler and foul the structured packing. Pressure‑swing‑induced fatigue was simulated in a laboratory autoclave cycling between 1.0 and 2.5 bara at a frequency of 0.1 Hz for 500 full‑amplitude cycles under a dry nitrogen environment at 25°C. After the cycling, the mean crush strength declined to 1.02 kg/mm and the fraction of pellets passing a 1.0 mm sieve increased from 0.2 wt% to 1.4 wt%, a value that exceeds the tube‑side pressure‑drop criterion of 0.5 wt% fines for safe decoking. Consequently, the operating procedures were revised to limit the number of full depressurization‑repressurization cycles to 12 per calendar year, with any additional cycle requiring a post‑cycle back‑flush of the tubes using DN 20 high‑velocity nitrogen nozzles at 15 barg to dislodge loose fines, a step that takes 90 minutes per tube. To monitor pellet degradation in situ, the shell‑side temperature profile across each tube bank is compared against a digital twin fed by 48 pilot‑tube thermocouples; a localized deviation of >4°C from the model’s predicted axial profile triggers an alert and a gas‑sampling traverse at the reactor outlet header for particle‑size analysis with an optical particle counter (sensitivity 0.3 μm), allowing early detection before fines accumulation creates a 25 mbar pressure‑drop excursion that would force an unplanned shutdown.
Comparative Stack Emission Profiles: Pre-Retrofit Photochlorination vs. Post-Retrofit Catalytic Process
ParameterPre-Retrofit (Photochemical)Post-Retrofit (Catalytic)Test Method
HCl mass concentration18–35 mg/Nm³0.8–1.5 mg/Nm³EN 1911:2010
Cl₂ equivalent2.4 mg/Nm³<0.1 mg/Nm³EPA Method 26A
Br₂ concentration6.8 mg/Nm³<0.05 mg/Nm³UV‑Vis impinger (NIOSH 6011)
Total volatile organic compounds (TVOC)45–80 mg/Nm³1.0–2.2 mg/Nm³EPA Method 18 / ISO 16000‑6:2021
Chloroform (CHCl₃)12 mg/Nm³<0.2 mg/Nm³EPA Method 18
Carbon tetrachloride (CCl₄)4.7 mg/Nm³<0.1 mg/Nm³EPA Method 18
Particulate matter (PM₁₀)8 mg/Nm³<3 mg/Nm³ISO 23210:2009
CO₂ equivalent (process vent)1 450 t/year (from NaClO brine decomposition)140 t/year (thermal oxidizer fuel)ISO 14064‑1:2018
The pressure relief system for the catalytic reactor must accommodate the worst‑case runaway reaction scenario in which the quench system fails to engage during a loss‑of‑cooling event, leading to an uncontrolled exotherm that vaporizes the liquid‑like reaction mixture trapped in the catalyst pores. Using the DIERS (Design Institute for Emergency Relief Systems) methodology and an Omega‑method two‑phase flow simulation calibrated with a high‑pressure adiabatic calorimeter (PHI‑TEC II) experiment on a 10 g sample of wetted catalyst, the maximum allowable relief pressure is set at 12.8 bara with a peak vapor generation rate of 2.4 kg/s of superheated HBr and organic vapors. The reactor is protected by a DN 80 rupture disc (graphite, burst rating 10.3 bara at 250°C, tolerance ±3%) coupled to a safety relief valve set at 10.5 bara with a certified discharge coefficient of 0.97 per ISO 4126‑1:2013. The relief tail pipe ( DN 100, schedule 80S, 316L with 3.2 mm PTFE lining) directs the two‑phase discharge into a 6.0 m³ horizontal blowdown tank with a 15% ullage, sized to contain the entire reactor inventory of 450 kg of catalyst and sorbed hydrocarbons plus 10 minutes of continued feed input, in accordance with API 521, 7th edition guidelines for reactor systems with an exothermic potential exceeding 800 kJ/kg. The blowdown tank is itself protected by a secondary rupture disc (DN 150, burst 8.0 bara) that vents to a dedicated high‑capacity scrubber column, which has been demonstrated in a full‑scale destructive test to capture 99.6% of entrained droplets larger than 5 μm. The entire overpressure protection loop is re‑validated every 36 months through a combination of bench‑testing of the relief valve, micrometer inspection of the graphite disc for corrosion pits deeper than 0.1 mm, and a 3‑D laser scan of the blowdown tank interior to verify wall thinning does not exceed 12% of the original 8.5 mm thickness specified in the ASME VIII‑1 design case. Published data for the specific two‑phase relief flow pattern through a packed bed of trilobe catalyst particles is limited, so the plant relies on a conservative discharge coefficient derating factor of 0.75 derived from small‑scale cold‑flow studies with a bed void fraction of 0.40, and a 1.5 × safety factor on the required relief area, resulting in the installation of a 6 200 mm² rupture disc bursting area instead of the theoretical 4 100 mm².
Regulatory Compliance and Standard Alignment Matrix for Retrofitted BCM Production Line
Regulation / StandardClause / RequirementEvidence of Compliance
EU IED 2010/75/EUBAT Conclusions for LVOC (2017/2117), BAT‑AEL 11 (HCl 5 mg/Nm³)Continuous stack monitoring data 0.8–1.5 mg/Nm³
REACH Regulation (EC) 1907/2006Annex XVII, entry 32: restrictions on CHCl₃ and CCl₄ content in BCM (<0.1 wt%)GC‑MS batch analysis, average 0.03 wt%
Seveso III Directive 2012/18/EUAnnex I, Part 1: HBr inventory threshold 5 t (lower tier)Recycle loop maximal hold‑up 1.2 t
ISO 14001:2015Clause 6.1.2: Environmental aspects — significant waste reductionAqueous waste stream eliminated (0 t vs. 1.4 t/t BCM)
ISO 50001:2018Clause 4.4.3: Energy review, specific consumption indicatorEnergy intensity reduced from 7.2 to 4.1 MJ/kg
ASTM D4179‑21Single pellet crush strength ≥0.85 kg/mmBatch mean 1.17 kg/mm, > limit
ASME VIII‑1Division 1, UG‑127: Pressure relief device sizingRupture disc area 6 200 mm², verification calculation available
IEC 61511‑1:2016Clause 11.4.2: SIL verification for quench systemSIL‑2 achieved with 2oo3 voting, proof test interval 12 months